G3(TH) G3(泰)
DESIGN & CONSTRUCTION DEPARTMENT
设计与施工部
SITE LOCATION 站点位置
SITE TAKING-OVER DATE 网站接管日期
SITE HANDOVER DATE 网站移交日期
SITE OPENING DATE 网站开放日期
SITE SIZE AREA 网站大小区域
GENERAL CONTRACTOR 总承包商
NOTE: 注意:
SUBDUED Terminal Pattaya SUBDUED Terminal 芭堤雅
Friday, 18 July 2025
2025 年 7 月 18 日星期五
Friday, 05 September 2025
星期五, 05 九月 2025
Thursday, 11 September 2025
2025 年 9 月 11 日星期四
100 sqm 100 平方米
V.S
| Vendor 供应商 |
Day Submission 日间提交 |
Final date 最终日期 |
No. of Days 不。天数 |
Task 任务 |
Status 地位 |
Remarks 言论 |
| Landlord 房东 |
|
|
|
Lease agreement, block pla, MEP base, Fitout Guide 租赁协议、街区 pla、MEP 基地、装修指南 |
COMPLETED |
|
| Subdued 制服 |
13-Jun-25 13-六月-25 |
|
|
Prelimerary Layout 初步布局 |
COMPLETED |
|
| Subdued 制服 |
19-Jun-25 19-六月-25 |
|
|
Initial drawing pack with 3D visuals 带有 3D 视觉效果的初始绘图包 |
COMPLETED |
|
| Landlord 房东 |
20-Jun-25 20 六月 25 |
|
|
Submission to LL 提交给 LL |
ON GOING 进行中 |
Waiting for LL approval 等待 LL 批准 |
| Subdued 制服 |
|
20-Jun-25 20 六月 25 |
|
Samples 样品 |
CRITICAL |
|
| Subdued 制服 |
|
13-Jun-25 13-六月-25 |
|
Floor layout 楼层布局 |
COMPLETED |
|
| Subdued 制服 |
|
13-Jun-25 13-六月-25 |
|
Lighting plan 照明计划 |
COMPLETED |
Waitng for Lighting references 等待 Lighting 参考 |
| Subdued 制服 |
|
20-Jun-25 20 六月 25 |
|
List of direct orders with BoQ BoQ 的直接订单清单 |
CRITICAL |
|
| G3 |
|
4-Jul-25 4-七月-25 |
|
Lighting order 照明顺序 |
NOT STARTED 未启动 |
| G3 |
|
4-Jul-25 4-七月-25 |
|
Flooring order 地板顺序 |
NOT STARTED 未启动 |
| Subdued 制服 |
|
1-Jul-25 1-七月-25 |
|
Final detailed drawing pack 最终详细绘图包 |
ON GOING 进行中 |
| V.S |
|
11-Jul-25 7月 11 日,25 |
|
Fitout works quotation 装修工程报价 |
NOT STARTED 未启动 |
|
| V.S |
|
11-Jul-25 7月 11 日,25 |
|
MEP Drawing MEP 绘图 |
NOT STARTED 未启动 |
|
| Subdued 制服 |
|
4-Jul-25 4-七月-25 |
|
Millwork drawing pack 木制品拉丝包 |
NOT STARTED 未启动 |
|
| Millworker 磨工 |
|
7-Jul-25 7月 7, 7月, 25 |
|
Quotation and millwork drawing approval 报价和木制品图纸批准 |
NOT STARTED 未启动 |
|
| Landlord 房东 |
|
18-Jul-25 7月 18, 25 |
|
Hoarding 囤积 |
NOT STARTED 未启动 |
Waiting for Subdued graphic 等待 Subdued 图形 |
| V.S |
|
18-Jul-25 7月 18, 25 |
|
Site takeover 网站接管 |
NOT STARTED 未启动 |
|
| Millworker 磨工 |
|
|
|
Mannequin and VM order with MW 含 MW 的人体模型和 VM 订单 |
NOT STARTED 未启动 |
Hangers quotation received 收到吊架报价 |
| File up 归档 |
|
|
|
Mobile storage racking 移动式仓储货架 |
NOT STARTED 未启动 |
|
| G3 |
|
|
|
IT requirement IT 要求 |
NOT STARTED 未启动 |
|
| G3 |
|
|
|
Security requirements 安全要求 |
NOT STARTED 未启动 |
|
| G3 |
|
|
|
BOH items requirements BOH 商品要求 |
NOT STARTED 未启动 |
|
| Millworker 磨工 |
10/7/2025 |
4/8/2025 |
25 days 25 天 |
Millwork production 木制品生产 |
NOT STARTED 未启动 |
To be defined with the Chinese millworker 与中国磨坊工人一起定义 |
| G3 |
5/8/2025 |
25-Aug-00 00 年 8 月 25 日 |
20 days 20 天 |
Delivery of millwork and clearance 木制品和清关的交付 |
NOT STARTED 未启动 |
|
| V.S |
26/8/2025 |
3-Sep-25 3-九月-25 |
7 days 7 天 |
Millwork installation 木制品安装 |
NOT STARTED 未启动 |
By GC 按 GC |
| V.S |
18-Jul-25 7月 18, 25 |
5-Sep-25 5-九月-25 |
7 weeks 7 周 |
Fitout and millwork Construction 装修和木制品施工 |
NOT STARTED 未启动 |
|
| G3 |
|
5-Sep-25 5-九月-25 |
|
Handover to Operations 移交给运营部门 |
ON SCHEDULE 按期 |
|
| G3 |
|
11-Sep-25 11-九月-25 |
|
Store Opening 开店 |
ON SCHEDULE 按期 |
|
| G3 |
|
|
|
Closing file 关闭文件 |
|
|
Vendor Day Submission Final date No. of Days Task Status Remarks
Landlord Lease agreement, block pla, MEP base, Fitout Guide COMPLETED
Subdued 13-Jun-25 Prelimerary Layout COMPLETED
Subdued 19-Jun-25 Initial drawing pack with 3D visuals COMPLETED
Landlord 20-Jun-25 Submission to LL ON GOING Waiting for LL approval
Subdued 20-Jun-25 Samples CRITICAL
Subdued 13-Jun-25 Floor layout COMPLETED
Subdued 13-Jun-25 Lighting plan COMPLETED Waitng for Lighting references
Subdued 20-Jun-25 List of direct orders with BoQ CRITICAL
G3 4-Jul-25 Lighting order NOT STARTED
G3 4-Jul-25 Flooring order NOT STARTED
Subdued 1-Jul-25 Final detailed drawing pack ON GOING
V.S 11-Jul-25 Fitout works quotation NOT STARTED
V.S 11-Jul-25 MEP Drawing NOT STARTED
Subdued 4-Jul-25 Millwork drawing pack NOT STARTED
Millworker 7-Jul-25 Quotation and millwork drawing approval NOT STARTED
Landlord 18-Jul-25 Hoarding NOT STARTED Waiting for Subdued graphic
V.S 18-Jul-25 Site takeover NOT STARTED
Millworker Mannequin and VM order with MW NOT STARTED Hangers quotation received
File up Mobile storage racking NOT STARTED
G3 IT requirement NOT STARTED
G3 Security requirements NOT STARTED
G3 BOH items requirements NOT STARTED
Millworker 10/7/2025 4/8/2025 25 days Millwork production NOT STARTED To be defined with the Chinese millworker
G3 5/8/2025 25-Aug-00 20 days Delivery of millwork and clearance NOT STARTED
V.S 26/8/2025 3-Sep-25 7 days Millwork installation NOT STARTED By GC
V.S 18-Jul-25 5-Sep-25 7 weeks Fitout and millwork Construction NOT STARTED
G3 5-Sep-25 Handover to Operations ON SCHEDULE
G3 11-Sep-25 Store Opening ON SCHEDULE
G3 Closing file | Vendor | Day Submission | Final date | No. of Days | Task | Status | Remarks |
| :--- | :--- | :--- | :--- | :--- | :--- | :--- |
| Landlord | | | | Lease agreement, block pla, MEP base, Fitout Guide | COMPLETED | |
| Subdued | 13-Jun-25 | | | Prelimerary Layout | COMPLETED | |
| Subdued | 19-Jun-25 | | | Initial drawing pack with 3D visuals | COMPLETED | |
| Landlord | 20-Jun-25 | | | Submission to LL | ON GOING | Waiting for LL approval |
| Subdued | | 20-Jun-25 | | Samples | CRITICAL | |
| Subdued | | 13-Jun-25 | | Floor layout | COMPLETED | |
| Subdued | | 13-Jun-25 | | Lighting plan | COMPLETED | Waitng for Lighting references |
| Subdued | | 20-Jun-25 | | List of direct orders with BoQ | CRITICAL | |
| G3 | | 4-Jul-25 | | Lighting order | NOT STARTED | |
| G3 | | 4-Jul-25 | | Flooring order | NOT STARTED | |
| Subdued | | 1-Jul-25 | | Final detailed drawing pack | ON GOING | |
| V.S | | 11-Jul-25 | | Fitout works quotation | NOT STARTED | |
| V.S | | 11-Jul-25 | | MEP Drawing | NOT STARTED | |
| Subdued | | 4-Jul-25 | | Millwork drawing pack | NOT STARTED | |
| Millworker | | 7-Jul-25 | | Quotation and millwork drawing approval | NOT STARTED | |
| Landlord | | 18-Jul-25 | | Hoarding | NOT STARTED | Waiting for Subdued graphic |
| V.S | | 18-Jul-25 | | Site takeover | NOT STARTED | |
| Millworker | | | | Mannequin and VM order with MW | NOT STARTED | Hangers quotation received |
| File up | | | | Mobile storage racking | NOT STARTED | |
| G3 | | | | IT requirement | NOT STARTED | |
| G3 | | | | Security requirements | NOT STARTED | |
| G3 | | | | BOH items requirements | NOT STARTED | |
| Millworker | 10/7/2025 | 4/8/2025 | 25 days | Millwork production | NOT STARTED | To be defined with the Chinese millworker |
| G3 | 5/8/2025 | 25-Aug-00 | 20 days | Delivery of millwork and clearance | NOT STARTED | |
| V.S | 26/8/2025 | 3-Sep-25 | 7 days | Millwork installation | NOT STARTED | By GC |
| V.S | 18-Jul-25 | 5-Sep-25 | 7 weeks | Fitout and millwork Construction | NOT STARTED | |
| G3 | | 5-Sep-25 | | Handover to Operations | ON SCHEDULE | |
| G3 | | 11-Sep-25 | | Store Opening | ON SCHEDULE | |
| G3 | | | | Closing file | | |